- Crushing & Proportioning : -
In cement manufacturing process the main raw material is
limestone, which is crushed and transported to the pre-blending
stockpile by means of a belt conveyor. After reclaiming it is
stored into the respective hoppers along with other Raw
materials. These raw materials then extracted in desired
proportion with the help of electronic weigh feeder &
transported to the raw mill for fine grinding.
|
 |
- Raw milling & Blending : -
The raw mill is a closed circuit ball mill equipped with high
efficiency separator. After grinding to 90 microns size the raw
meal is send to the continuous blending silos (CFC) for
homogenization & extracted by means of load cell hopper for
feeding to the kiln pre heaters.
|
 |
- Pyro processing : -
It consists of series of low-pressure drop, pre heater cyclones
generally with fluidized bed calciner, where the calcinations
begin and material goes into the Rotary Kiln and after
clinkerization the hot material is sent to the cooler for its
cooling. The cooler is efficiently designed to recover maximize
heat while cooling the hot clinker which is then crushed &
sent to the stock pile for intermediate storage.
|
 |
- Burning :-
The required temperature for the clinkerisation is about
1500oC, which can be attained either by Coal, Gas or Oil. The
burner is fuel-efficient specially designed Multi channel type
for uniform burning.
|
 |
- Cement milling, Storage & Packing:-
The clinker mixed with app. 5% of gypsum is sent to the cement
mill (Ball Mill) for fine grinding to produce cement. It is then
transported to CFC silo for blending & storage and is packed
in the bags with helps of auto packers & transported to the
market for sale
|